Sections 226 and 708

Offshore Petroleum and Greenhouse Gas Storage Act 2006

 

APPLICATION FOR VARIATION OF A PIPELINE LICENCE

 

I, GRAEME ALBERT WATERS, the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth–Victoria Offshore Petroleum Joint Authority hereby give notice pursuant to sections 226 and 708 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 that an application has been received from

 

Esso Australia Resources Pty Ltd

(ABN 62 091 829 819)

 

BHP Billiton Petroleum (Bass Strait) Pty. Ltd.

(ABN 29 004 228 004)

 

 for the variation of Pipeline Licence VIC/PL17 in the offshore area of Victoria, as set out below.

 

Pursuant to subsection 226(3) of the Act, a person may make a written submission to the Titles Administrator about this application within 30 days from the date of this notice.

 

This notice takes effect on the day on which it appears in the
Australian Government Gazette.

 

Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006

of the Commonwealth of Australia.

 

GRAEME ALBERT WATERS

TITLES ADMINISTRATOR

ON BEHALF OF THE COMMONWEALTH–VICTORIA

OFFSHORE PETROLEUM JOINT AUTHORITY

 

 


 

APPLICATION FOR VARIATION OF

PIPELINE LICENCE VIC/PL17

 

 The application seeks to affect the following administrative amendments to the licence:

 

 

Pipeline Duration, Interpretation and Conditions

 

1.         Vary the duration of the licence from a fixed tern to an indefinite term to reflect legislative amendment.

 

2.         Where possible, removing references to the former Designated Authorities or the ‘said Manager’.

 

 

 

Route of the Pipeline

 

3.         Add the As-Constructed Pipeline Co-ordinates.

 

4.         Add the Route Map.

 

 

Specifications and Further Conditions

 

5.         Update the pipeline design details and parameters, including reference to relevant Australian Standards, to reflect the as-constructed Flounder to Tuna pipeline.

 

6.         Delete conditions relating to pipeline specifications, performance, reporting and approval requirements that are no longer required or have been superseded under the current regulatory regime (and are regulated by the National Offshore Petroleum Safety and Environmental Management Authority).

 

 

As-Constructed Pipeline Co-ordinates

 

The route of the Flounder to Tuna pipeline is described in the table below, and displayed in the map below, commencing at the flange immediately downstream of the LVO on the Flounder platform and terminating at the first flange upstream of the FVO on the Tuna platform. Coordinates are based on Geodetic Datum of Australia (GDA94).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

POINT ID

DESCRIPTION

EASTING

NORTHING

1

LVO Flounder Manifold

625859.5

5758705

2

Inflection Point 01

625866.6

5758705.4

3

Inflection Point 02

625873.3

5758735.3

4

Inflection Point 03

625867.5

5758784.4

5

Inflection Point 04

625833

5758787

6

Inflection Point 05

625786

5758799

7

Inflection Point 06

625783

5758817

8

Inflection Point 07

625829

5762223

9

Inflection Point 08

625863

5762244

10

Inflection Point 09

626086.7

5765652

11

Inflection Point 10

626118.3

5765644.9

12

West Tuna Fluid Umbilical Crossing

625459.8

5772194.2

13

KPA350 South Gas Pipeline Crossing

625455.8

5772214.9

14

KPA350 North Gas Pipeline Crossing

625446.1

5772265.8

15

West Tuna Electrical Umbilical Crossing

625441.2

5772291.4

16

Inflection Point 11

625214

5773082

17

Inflection Point 12

624587.1

5774202.3

18

Inflection Point 13

624365.9

5774389.1

19

FVO Tuna Manifold

624358.2

5774389.1

 

Coordinate set above is based on GDA94 / MGA Zone 55, survey of pipeline centreline.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Map depicting the "as built" route of pipeline VIC/PL17 commencing at the Flounder platform and terminating at the Tuna platform.