COMMONWEALTH OF AUSTRALIA

 

Section 708

Offshore Petroleum and Greenhouse Gas Storage Act 2006

 

APPLICATION FOR VARIATION OF A PIPELINE LICENCE

 

I, GRAEME ALBERT WATERS, the National Offshore Petroleum Titles Administrator, on behalf of the Commonwealth–Western Australia Offshore Petroleum Joint Authority, hereby give notice pursuant to section 708 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 (the Act) that an application has been received from

 

 

 

Woodside Energy Julimar Pty Ltd

(ABN 56 130 391 365)

 

Kufpec Australia (Julimar) Pty Ltd

(ABN 38 139 500 502)

 

 

 

for the variation of a Petroleum Pipeline Licence WA-26-PL in the offshore area of Western Australia, as set out below.

 

Pursuant to subsection 226(3) of the Act, a person may make a written submission to the Titles Administrator about this application within 30 days from the date of this notice.

 

This notice takes effect on the day on which it appears in the Australian Government Gazette.

 

Made under the Offshore Petroleum and Greenhouse Gas Storage Act 2006

of the Commonwealth of Australia.

 

 

GRAEME ALBERT WATERS

TITLES ADMINISTRATOR

ON BEHALF OF THE COMMONWEALTH-WESTERN AUSTRALIA

OFFSHORE PETROLEUM JOINT AUTHORITY


APPLICATION FOR A VARIATION OF

PETROLEUM PIPELINE LICENCE WA-26-PL

 

Julimar-Brunello Pipeline

 

Pipeline Route Map

 

Title: Pipeline Route Map - Description: This is a map of the varied pipeline route.

Pipeline Co-ordinates

 

BRUA Manifold

 

Feature ID

Feature Description

Easting

Northing

Current Status

1.0

BRUA Manifold – Centre

311 922.35

7 784 154.66

Design

BRUA  Crossover Manifold

 

Feature ID

Feature Description

Easting

Northing

Current Status

2.0

BRUA Crossover Manifold - Centre

311 986.91

7 784 092.84

Design

Brunello Production Pipeline

 

Feature ID

Feature Description (Note 1)

Easting

Northing

Current Status

3.0

Production FLET

312 054.23

7 784 093.32

    As built

3.1

Displacement Initiator CRB B01

312 743.96

7 784 490.57

As built

3.2

Displacement Initiator CRB B02

313 415.79

7 784 925.59

As built

3.3

Displacement Initiator CRB B03

314 223.88

7 785 514.17

As built

3.4

Displacement Initiator CRB B04

315 072.65

7 786 044.29

As built

3.5

Displacement Initiator CRB B05

315 869.37

7 786 657.01

As built

3.6

Displacement Initiator CRB B06

316 705.58

7 787 213.49

As built

3.7

Displacement Initiator CRB B07

317 526.58

7 787 871.41

As built

3.8

Displacement Initiator CRB B08

318 281.73

7 788 605.79

As built

3.9

Displacement Initiator CRB B09

319 057.18

7 789 237.27

As built

3.10

Displacement Initiator CRB B10

319 772.35

7 789 930.98

As built

3.11

Displacement Initiator CRB B11

320 406.43

7 790 638.49

As built

3.12

Displacement Initiator CRB B12

321 195.69

7 791 250.77

As built

3.13

Displacement Initiator CRB B13

321 996.87

7 791 662.99

As built

3.14

Displacement Initiator CRB B14

322 835.04

7 791 990.54

As built

3.15

Displacement Initiator CRB B15

323810.60

7 792 256.11

As built

3.16

Displacement Initiator CRB B16

324 896.68

7 792 432.76

As built

3.17

Displacement Initiator CRB B17

325 963.04

7 792 630.54

As built

3.18

Displacement Initiator CRB B18

326 815.06

7 792 927.64

As built

3.19

Displacement Initiator CRB B19

327 862.16

7 793 205.29

As built

3.20

Displacement Initiator CRB B20

328 822.21

7 793 749.46

As built

3.21

Displacement Initiator CRB B21

329 387.94

7 794 389.74

As built

3.22

Displacement Initiator CRB B22

329 948.20

7 794 969.56

As built

3.23

Flowline Tie-in Flange

330 692.49

7 795 596.57

As built

3.24

Wheatstone Platform JDP SSIV (centre)

330 760.87

7 795 574.98

As built

Julimar Production Pipeline

 

Feature ID

Feature Description (Note 1)

Easting

Northing

Current Status

4.0

Production FLET

312 052.92

7 784 073.31

As built

4.1

Displacement Initiator CRB J01

312 741.76

7 784 452.14

As built

4.2

Displacement Initiator CRB J02

313 422.51

7 784 874.40

As built

4.3

Displacement Initiator CRB J03

314 230.70

7 785 463.80

As built

4.4

Displacement Initiator CRB J04

315 079.08

7 785 992.31

As built

4.5

Displacement Initiator CRB J05

315 874.78

7 786 605.64

As built

4.6

Displacement Initiator CRB J06

316 712.06

7 787 161.41

As built

4.7

Displacement Initiator CRB J07

317 535.21

7 787 819.61

As built

4.8

Displacement Initiator CRB J08

318 292.87

7 788 552.00

As built

4.9

Displacement Initiator CRB J09

319 104.13

7 789 218.09

As built

4.10

Displacement Initiator CRB J10

319 816.99

7 789 912.07

As built

4.11

Displacement Initiator CRB J11

320 424.03

7 790 587.95

As built

4.12

Displacement Initiator CRB J12

321 200.01

7 791 188.77

As built

4.13

Displacement Initiator CRB J13

322 043.95

7 791 625.08

As built

4.14

Displacement Initiator CRB J14

322 811.57

7 791 925.33

As built

4.15

Displacement Initiator CRB J15

323 833.33

7 792 206.02

As built

4.16

Displacement Initiator CRB J16

324 921.34

7 792 385.50

As built

4.17

Displacement Initiator CRB J17

325 958.14

7 792 569.44

As built

4.18

Displacement Initiator CRB J18

326 852.13

7 792 890.68

As built

4.19

Displacement Initiator CRB J19

327 892.60

7 793 182.78

As built

4.20

Displacement Initiator CRB J20

328 829.17

7 793 707.76

As built

4.21

Displacement Initiator CRB J21

329 430.72

7 794 387.47

As built

4.22

Displacement Initiator CRB J22

329 985.69

7 794 965.38

As built

4.23

Flowline Tie-in Flange

330 695.05

7 795 583.35

As built

4.24

Wheatstone Platform JDP SSIV (centre)

330 760.87

7 795 574.98

As built

Wheatstone Platform

Feature ID

Feature Description

Easting

Northing

Current Status

5.1

Wheatstone Platform Centre

330 862.0

7 795 521.3

As built

 

Notes:

1)       Between the FLET and the tie-in flange, the flowline has been installed around the displacement initiator structures; which provides fixed points of reference along the route.

 

 

 

 

Pipeline Design Temperatures

 

·         Maximum design temperature: 133°C

·         Minimum design temperature: -20°C