actions determined as requiring approval (EPBC Act s.75)

Reference

Title

Controlling Provisions

Date

2025/10228

Atlas Iron Pty Ltd / Mining / N/A / Western Australia / Atlas Iron Pty Ltd - Sanjiv Ridge Stage 1 Below Groundwater Table Mining

  • Listed threatened species and communities (sections 18 & 18A)

15/08/2025

 

actions determined as NOT requiring approval (EPBC Act s.75)

Reference

Title

Date

2025/10174*

Northern Minerals Limited / Mining / 160 km southeast of Halls Creek, WA within boundary of Mining Lease M 80/627 issued under the Mining Act 1978 (Att_1B_Figure 2 Project Area) / Western Australia / Browns Range Heavy Rare Earths Project - Heavy Rare Earth Bagging Facility and Concentrate Storage Area

1/08/2025

 

* Actions which are not controlled actions provided they are undertaken in a particular manner. Further information on provision and manner specified is available from https://epbcpublicportal.environment.gov.au/all-referrals/

 

Assessment Approach (EPBC Act s.87)

Reference

Title

Assessment Approach

Date

2021/8993

Bowen Pipeline Company Pty Ltd / Water Management and Use / between the Burdekin River at Home Hill to Bowen in the Whitsunday Region / Queensland / Bowen Pipeline

Preliminary Documentation

15/08/2025

2025/10228

Atlas Iron Pty Ltd / Mining / N/A / Western Australia / Atlas Iron Pty Ltd - Sanjiv Ridge Stage 1 Below Groundwater Table Mining

Public Environment Report

15/08/2025

 

DECISION ON APPROVAL (EPBC Act s.133)

Reference

Title

Approval Decision

Date

2023/09666

Tasmanian Irrigation Pty Ltd / Water Management and Use / Latrobe Council region - between Devonport and Port Sorell, and as far south as Sassafras / Tasmania / Sassafras - Wesley Vale Irrigation Scheme Augmentation

Approved with conditions

15/08/2025

 

OUTCOME OF REQUEST FOR RECONSIDERATION OF S75(1) DECISION (EPBC Act s.78C)

Reference

Title

Reconsideration Decision

Date

2012/6406

Department Of Primary Industries Parks Water and ENVIRONMENT / Aquaculture / Macquarie Harbour / Tasmania / Marine Farming Expansion, Macquarie Harbour, TAS

Not a Controlled Action - Particular Manner

13/08/2025

 

variation of conditions of approval (EPBC Act s.143)

Reference

Title

Date

2019/8487

Department Of Transport / Transport - Land / Multiple lots / Victoria / Healesville - Koo Wee Rup Road Upgrade, Vic

15/08/2025

2010/5757

Boral Resources Qld Pty Limited / Mining / Western side of Pacific Motorway, 5km from Burleigh / Queensland / Extraction and processing of hard rock at Gold Coast Quarry

20/08/2025

 


NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))

Reference

Title

Extended to

Date

2021/8968

Stevens Holdings Pty Ltd / Residential Development / 414 Old Maitland Rd, Mardi / New South Wales / 414 Old Maitland Road Residential Subdivision

12/09/2025

15/08/2025

2021/9050

Fosterville Gold Mine Pty Ltd / Mining / McCormicks Road, Fosterville / Victoria / Fosterville Gold Mine Sustained Operations Project Sustained Operations Project

3/10/2025

15/08/2025

2019/8587

Lendlease Communities (Figtree Hill No. 3) Pty Limited / Residential Development / west of Appin Road, near Campbelltown / New South Wales / Mt Gilead Stage 2 Residential Development

13/10/2025

18/08/2025

 

Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.