DEPARTMENT OF CLIMATE CHANGE, ENERGY, THE ENVIRONMENT AND WATER
Environment Protection and Biodiversity Conservation Act 1999
EPBC Act Part 7-9 decisions published, 19/05/2025 to 25/05/2025
For further information see the referrals list at https://epbcpublicportal.environment.gov.au/all-referrals/
and type the reference number in the Filter by Referral Number box
actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2025/10116 | Zuri Properties Pty Ltd / Residential Development / 2-34 & 36-62 Junction Road, Karalee QLD 4306 / Queensland / Urban Development, Junction Road, Karalee |
| 19/05/2025
|
2025/10159 | Goodman Property Services (Aust) Pty Limited / Commercial Development / 1 Honeman Close, Huntingwood NSW 2148 / New South Wales / Honeman Close Warehouse Facility (SSD-79500208) |
| 19/05/2025 |
2025/10155 | McCloy Project Management Pty Ltd / Residential Development / 587 Newline Road, Raymond Terrace, NSW / New South Wales / Monarchs Rise Residential Subdivision |
| 20/05/2025 |
2025/10166 | Burdekin Solar Farm Pty Ltd as trustee for the Burdekin Genesis Project Trust / Energy Generation and Supply (non-renewable) / 207 Woodhouse Road, Mulgrave Queensland. / Queensland / Burdekin BESS and Transmission Line |
| 20/05/2025 |
2025/10164 | Tilt Renewables Devco Pty Ltd / Energy Generation and Supply (renewable) / Lincoln Highway, Middleback Range, 10 km west of Whyalla in South Australia within the Whyalla City Council area. / South Australia / Nonowie Wind Farm |
| 21/05/2025 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2025/10160 | Weasel Solar Farm Pty Ltd / Energy Generation and Supply (renewable) / 3415 Highland Lakes Road, Bothwell TAS 7030 / Tasmania / Weasel Solar Farm | 20/05/2025 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2025/10116 | Zuri Properties Pty Ltd / Residential Development / 2-34 & 36-62 Junction Road, Karalee QLD 4306 / Queensland / Urban Development, Junction Road, Karalee | Preliminary Documentation | 19/05/2025 |
2025/10155 | McCloy Project Management Pty Ltd / Residential Development / 587 Newline Road, Raymond Terrace, NSW / New South Wales / Monarchs Rise Residential Subdivision | Preliminary Documentation | 20/05/2025 |
2025/10166 | Burdekin Solar Farm Pty Ltd as trustee for the Burdekin Genesis Project Trust / Energy Generation and Supply (non-renewable) / 207 Woodhouse Road, Mulgrave Queensland. / Queensland / Burdekin BESS and Transmission Line | Preliminary Documentation | 20/05/2025 |
2025/10164 | Tilt Renewables Devco Pty Ltd / Energy Generation and Supply (renewable) / Lincoln Highway, Middleback Range, 10 km west of Whyalla in South Australia within the Whyalla City Council area. / South Australia / Nonowie Wind Farm | Preliminary Documentation | 21/05/2025 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2023/09524 | Sealark Pty Limited / Residential Development / Lot 1 DP 1279350, Lot 2 DP 1279350 AND Lot 3 DP1279350, Culburra Beach and Wollumboola / New South Wales / West Culburra Residential Subdivision | Approved with conditions | 23/05/2025 |
OUTCOME OF REQUEST FOR RECONSIDERATION OF S75(1) DECISION (EPBC Act s.78C)
Reference | Title | Reconsideration Decision | Date |
2018/8335 | Woodside Energy Ltd. / Mining / De Wit Location: Lot 199, 197, 379, 380, 655, 195, 151, 204 / Western Australia / North West Shelf Project Extension, Carnarvon Basin, WA | Controlled Action | 20/05/2025 |
NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))
Reference | Title | Extended to | Date |
2024/10031 | Department Of Defence / Commonwealth / HMAS Stirling, Garden Island / Western Australia / Submarine Rotational Force – West, Priority Infrastructure Works | 29/05/2025 | 15/05/2025 |
2022/09424 | Department of State Growth / Transport - Land / Midland Highway – north of West Street, Campbell Town to Esk Main Road, Conara / Tasmania / Midland Highway Upgrade - Campbell Town North Portion B | 16/06/2025 | 22/05/2025 |
lapsed proposals (EPBC Act s.155)
Reference | Title | Date |
2006/2734 | Darwin Clean Fuels Pty Ltd / Mining / Darwin Business Park / Northern Territory / Condensate Processing Facility, East Arm | 14/05/2025 |
2014/7299 | Tenax Energy Pty Ltd / Energy Generation and Supply (renewable) / within Clarence Strait approx 50km NE Darwin / Northern Territory / Tropical Tidal Testing Centre, Clarence Strait, 50km NE Darwin | 14/05/2025 |
2015/7604 | TNG Ltd / Mining / Middle Arm Peninsula, Darwin / Northern Territory / Establishment and operation of a refinery at Darwin, NT | 14/05/2025 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.