DEPARTMENT OF CLIMATE CHANGE, ENERGY, THE ENVIRONMENT AND WATER
Environment Protection and Biodiversity Conservation Act 1999
EPBC Act Part 7-9 decisions published, 04/11/2024 to 10/11/2024
For further information see the referrals list at https://epbcpublicportal.environment.gov.au/all-referrals/
and type the reference number in the Filter by Referral Number box
actions determined as requiring approval (EPBC Act s.75)
Reference | Title | Controlling Provisions | Date |
2024/09983 | BM Alliance Coal Operations Pty Limited / Energy Generation and Supply (non-renewable) / 831 Peak Downs Mine Road, Winchester / Queensland / Peak Downs Mine Power Line Realignment Project |
| 6/11/2024 |
actions determined as NOT requiring approval (EPBC Act s.75)
Reference | Title | Date |
2024/09899 | Robert Travis / Tourism and Recreation / 4A Vardon rd, Fern Bay / New South Wales / 1440- Newcastle Golf Course Alterations | 4/11/2024 |
2024/09973 | B. & J. CATALANO PTY LTD / Mining / Lot 41 and 42 Eatha Rd, Chittering / Western Australia / Donningtons Gravel Quarry | 5/11/2024 |
Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2024/09983 | BM Alliance Coal Operations Pty Limited / Energy Generation and Supply (non-renewable) / 831 Peak Downs Mine Road, Winchester / Queensland / Peak Downs Mine Power Line Realignment Project | Preliminary Documentation | 6/11/2024 |
variation of conditions of approval (EPBC Act s.143)
Title | Date | |
2015/7436 | ARAFURA RESOURCES LIMITED / Mining / Central Australia / Northern Territory / Nolans Rare Earth Project, NT | 24/10/2024 |
2017/7881 | Australia Pacific LNG Pty Limited / Mining / approximately 70km northeast of Roma / Queensland / Spring Gully CSG North West and North East Development, Surat Basin, Qld | 6/11/2024 |
NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))
Reference | Title | Extended to | Date |
2023/09649 | DEPARTMENT OF DEFENCE / Commonwealth Development / Blamey Barracks Kapooka, Camp Access Road, Kapooka / New South Wales / Blamey Barracks Kapooka Redevelopment Project | 22/11/2024 | 6/11/2024 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.