Assessment Approach (EPBC Act s.87)
Reference | Title | Assessment Approach | Date |
2021/8971 | WESTERN AREAS LIMITED / Mining / Forrestania / Western Australia / New Morning Underground Nickel Deposit Project | Preliminary Documentation | 7/06/2022 |
2021/9085 | Newcrest Operations Limited / Mining / approx. 450 km south east of the town of Port Hedland / Western Australia / Havieron Project | Preliminary Documentation | 5/07/2022 |
DECISION ON APPROVAL (EPBC Act s.133)
Reference | Title | Approval Decision | Date |
2021/8958 | Goyder Wind Farm 1 Pty Ltd / Energy Generation and Supply (renewable) / Burra, Hanson, Porter Lagoon, Koonoona and Apoinga / South Australia / Goyder South Hybrid Renewable Energy Facility - Wind Farm 1A, 10km south Burra | Approved with conditions | 5/07/2022 |
variation of conditions of approval (EPBC Act s.143)
Title | Date | |
2011/6229 | SIMTA / Transport - Land / Moorebank Avenue / New South Wales / Moorebank Intermodal Terminal Facility | 27/06/2022 |
2020/8837 | Rye Park Renewable Energy Pty Ltd / Energy Generation and Supply (renewable) / near Yass / New South Wales / Rye Park Wind Farm | 30/06/2022 |
NOTICE OF EXTENSION OF TIME (EPBC Act s.130(4))
Reference | Title | Extended to | Date |
2020/8773 | ACCIONA ENERGY AUSTRALIA GLOBAL PTY LTD / Energy Generation and Supply (renewable) / Lot 2 SP301578 and Lot 1 SP157677 / Queensland / Aldoga Solar Farm Project | 29/07/2022 | 6/07/2022 |
2018/8330 | ROY HILL IRON ORE PTY LTD / Mining / M46/518, M46/519, L46/104, L46/110, L46/129, L46/141, L46/142, L47/346, L47/347, L47/642, L47/735 / Western Australia / Roy Hill Iron Ore Mine expansion, Pilbara Region, WA | 5/08/2022 | 7/07/2022 |
Some public notifications on the Internet and in the Gazette relating to the processing of referrals for approval under Chapter 4 of the Environment Protection and Biodiversity Conservation Act 1999 may occasionally be missed in processing by the Department of Climate Change, Energy, the Environment and Water or may not meet timeframes for notification. The Department of Climate Change, Energy, the Environment and Water has implemented systems and ongoing quality assurance procedures to minimise any risk of missing a notification within the required timeframe. Where a missed notification is identified the practice will be to notify these even though the timeframe for notification has lapsed. This will ensure that the history of notifications for each referral is available to the public. The Department of Climate Change, Energy, the Environment and Water regrets any inconvenience that may be caused by a missed notification. Please note that late notifications have not affected subsequent processing of referrals or assessments and they do not affect decisions made.